Gantt charts
A Gantt chart, or bar chart, is the most familiar way to show a schedule. Each activity is a horizontal bar on a time scale, starting at its planned start date and ending at its planned finish. It is easy to read, which is why it is used in site offices, progress meetings and reports to clients and owners. Henry Gantt popularised it a century ago, and it remains the standard output of every scheduling program.
A plain bar chart shows when work is planned but not why. It does not show logical dependencies, so it is hard to see the effect of a delay to one activity on others. Modern scheduling tools therefore draw linked Gantt charts, in which dependency arrows connect bars and the critical path is highlighted, combining the readability of bars with the logic of a network. Bars can show baseline and actual dates side by side, percent complete, float, milestones (shown as diamonds) and summary bars for WBS groups.
Good practice keeps charts at the right level of detail for the audience: a one-page summary with major milestones for senior management, a level-3 programme for the project team and three-week look-ahead charts for supervisors. Progress is marked with a data date line; bars that fall to its left without being complete are behind schedule. Resource histograms below the bars show manpower or equipment needs over time, which helps spot unrealistic peaks.
Duration = finish − start (working days)Percent complete (physical) = work done / total workLook-ahead window: typically 3 weeks rolling
Problem. A slab activity is planned for 12 working days starting day 20. On the data date, day 26, it is 40 percent complete. Is it on schedule, and what is the forecast finish if the rate stays the same?
- Planned progress at day 26: 6 of 12 days elapsed, so 50 percent.
- Actual 40 percent, so it is behind by 10 percent of the work (about 1.2 days).
- Rate = 40 percent in 6 days, so 100 percent needs 15 days.
- Forecast finish = day 20 + 15 = day 35 instead of day 32.
Answer. Behind schedule; forecast finish about day 35 (3 days late)
Quick quiz
1What is the main limitation of a plain bar chart?
It does not show logical dependencies between activities.
2How is a milestone shown?
As a diamond, with zero duration.
3What is a three-week look-ahead?
A short-term detailed bar chart used by site supervisors.
- IS 15883 (series) (India): Guidelines for construction project management, one part per knowledge area.
Clauses and documents to read
- IS 15883 (Part 2):2013 (time management)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- B. C. Punmia, K. K. Khandelwal, Project Planning and Control with PERT and CPM, Laxmi Publications, latest edition.
- J. W. Hinze, Construction Planning and Scheduling, Pearson, latest edition.