Parts of a track
A railway track is a load-spreading system, like a road pavement, but built from discrete parts. Rails guide the wheels and carry the load. Fastenings hold the rails to the sleepers at the right gauge and inclination while allowing small movements. Sleepers, today mostly prestressed concrete, spread the load and keep the gauge. Ballast, crushed stone below and between the sleepers, distributes the load, resists sideways movement, and drains water away. Under the ballast is the formation, a prepared layer of compacted soil.
Indian Railways' main lines use broad gauge, 1 676 mm between the inner faces of the rails. Most newer metro systems and high-speed lines use standard gauge, 1 435 mm, although the earliest Delhi Metro lines were built to broad gauge.
Long welded rails remove most fishplate joints, giving a smoother, quieter ride. Their thermal expansion is restrained by ballast and fastenings, with switch expansion joints at the ends.
Ballastless track, a concrete slab with direct fastenings, is used in tunnels, on viaducts and on high-speed lines where accuracy and low maintenance matter.
Thermal free expansion ΔL = α L ΔT, with α for rail steel about 11.5 × 10⁻⁶ per °C
Problem. A 13 m rail heats by 30 °C. If free, how much does it lengthen?
- ΔL = 11.5 × 10⁻⁶ × 13 000 × 30 = 4.5 mm.
Answer. About 4.5 mm
Quick quiz
1Indian broad gauge?
1 676 mm.
2Three jobs of ballast?
Spread load, hold track in place, and drain.
3Why use long welded rails?
Fewer joints, smoother ride and less maintenance.
- Indian Railways Permanent Way Manual (India): Standards and practice for track laying and maintenance.
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
Related videos
Why rail tracks have gaps
Steel grows in heat; gaps and modern welded rail handle it differently.
Sabarmati bullet-train river bridge
How the high-speed rail viaduct crosses the Sabarmati: foundations in the riverbed, piers, then spans placed on top.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- Satish Chandra, M. M. Agarwal, Railway Engineering, Oxford University Press, latest edition.
- C. Esveld, Modern Railway Track, MRT-Productions, 2nd edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.