There is no single way to build a tunnel. The method follows the ground, the depth, the length and what is above.

In hard rock, drill-and-blast is still common: drill a pattern of holes, charge them, blast, ventilate, remove the broken rock, then install support. The New Austrian Tunnelling Method (NATM) is a design philosophy as much as a method: excavate in stages, apply flexible support such as shotcrete and rock bolts soon after, and monitor deformation so that the ground carries much of its own load.

Diagram: Indiacon original, not to scale.

Tunnel boring machines (TBMs) cut the full face mechanically. In soft ground under cities, closed-face TBMs balance the earth and water pressure at the face and erect precast segment rings behind, limiting surface settlement. They suit long tunnels where their high set-up cost pays back.

Cut-and-cover builds a box in an open excavation and backfills over it; it suits shallow metro stations. Immersed tunnels are made of precast elements floated out and sunk into a dredged trench across a river or strait.

Quick quiz

1What is the core idea of NATM?

Mobilise the ground's own strength with early flexible support and monitoring.

2Where does cut-and-cover suit?

Shallow structures such as metro stations.

3How are immersed tunnel elements placed?

Floated out and lowered into a dredged trench.

Code note
  • IRC:SP:91 (India): Guidelines for road tunnels.

Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.

Related videos

Short

Road tunnel through a mountain: drill, blast, NATM

Excavate in rounds and let the rock help support itself.

Watch on YouTube →

Short

Cut-and-cover tunnel

Dig from the surface, build the box, cover it back.

Watch on YouTube →

Long video

Atal Tunnel, Rohtang

A single-tube road tunnel under the Pir Panjal that keeps a mountain valley reachable through winter.

Watch on YouTube →

Long video

Fehmarnbelt: 18 km under the sea

Precast tunnel elements floated out and lowered into a dredged trench, Denmark to Germany.

Watch on YouTube →

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • J. O. Bickel, T. R. Kuesel, E. H. King, Tunnel Engineering Handbook, Chapman and Hall, 2nd edition.
  • E. Hoek, E. T. Brown, Underground Excavations in Rock, Institution of Mining and Metallurgy, 1980.

Free and official sources

All references for this subject →

Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.