Cash flow and S-curves
Cash flow is the timing of money coming in and going out. A project can be profitable on paper yet fail because money runs out halfway. For an owner, cash flow forecasts show how much funding is needed each month. For a contractor, they show how much working capital must be arranged between paying suppliers and wages and receiving payment for certified work.
Plotting cumulative cost against time usually gives an S-shaped curve: slow at the start during mobilisation and early works, steep in the middle when most trades are working, flattening towards completion as finishing and testing take place. The planned S-curve, drawn from the cost-loaded schedule, is the baseline. Actual cost and earned value curves are drawn on the same axes during the project. The gap between curves shows cost and schedule variance at a glance. Typical S-curve shapes from past projects let planners sanity-check a new schedule.
A contractor's cash position depends on the payment terms: monthly running bills, the certification period, retention money held back (often around 5 percent until defects liability ends), mobilisation advances and their recovery, and price adjustment. Outflows include materials paid on delivery or credit, subcontractors and plant. The cumulative cash curve dips below zero early in the job; the deepest point is the peak working capital requirement, and its cost in interest is a real project cost.
Negotiate a mobilisation advance and shorter certification periods; both cut peak working capital.
Cumulative cost curve: S-shapeNet cash = cumulative receipts − cumulative paymentsReceipt in month n ≈ (value certified in month n − lag) × (1 − retention)Peak working capital = most negative net cash
Problem. A contractor does ₹2, 4, 6 and 4 crore of work in months 1 to 4. Costs are paid in the same month. Bills are paid one month late with 5 percent retention. Find the net cash at the end of each month.
- Cumulative cost: 2, 6, 12, 16.
- Receipts: month 2: 1.9; month 3: 3.8; month 4: 5.7. Cumulative: 0, 1.9, 5.7, 11.4.
- Net cash: −2.0, −4.1, −6.3, −4.6 crore.
- Peak working capital needed ≈ ₹6.3 crore at month 3 (before month-5 receipt of 3.8).
Answer. Net cash −2.0, −4.1, −6.3, −4.6 crore; peak need about ₹6.3 crore
Quick quiz
1Why is the cumulative cost curve S-shaped?
Slow start, rapid middle, slow finish.
2What is retention money?
A percentage of each payment held back until defects are cleared.
3What is peak working capital?
The most negative point of the contractor's cumulative net cash.
- IS 15883 (series) (India): Guidelines for construction project management, one part per knowledge area.
Clauses and documents to read
- IS 15883 (Part 3):2015 (cost management)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- Q. W. Fleming, J. M. Koppelman, Earned Value Project Management, Project Management Institute, latest edition.
- K. K. Chitkara, Construction Project Management, McGraw Hill Education (India), latest edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.