Ground improvement

Advanced and Design Geotechnical and Foundation Engineering Reviewed 24 Oct 2026 2 min read

When the ground is too soft, loose or compressible to carry a structure economically, it can often be improved instead of bypassed with deep piles. The choice depends on soil type, depth of the problem layer, the load and the time available. Improvement aims to increase strength, reduce settlement, speed up consolidation or prevent liquefaction.

For soft clays, preloading with an embankment surcharge squeezes out water and pre-consolidates the soil, so that later settlement under the real load is small. Clays drain slowly, so prefabricated vertical drains, band drains pushed in at a close grid, shorten the drainage path from the layer thickness to the drain spacing and cut consolidation time from years to months. Vacuum preloading applies suction instead of fill.

Diagram: Indiacon original, not to scale.

Stone columns, holes formed by vibro-probes and backfilled with compacted gravel, reinforce soft soils, act as drains and stiffen the ground under tanks and embankments; IS 15284 (Part 1) gives guidance. In loose sands, vibro-compaction densifies the ground, and dynamic compaction, repeatedly dropping a heavy weight from a height, densifies deeper layers; its depth of influence grows with the square root of the energy per drop. Grouting, deep soil mixing with cement and jet grouting create stronger columns or blocks.

Every scheme needs trials and verification: settlement plates, piezometers, penetration tests before and after, and load tests, so that the improved ground is shown to meet the design.

Tip

Install monitoring before improvement starts so that the baseline is known.

Key formulas
  • Dynamic compaction depth (Ménard, empirical): D ≈ n √(W H), W in tonnes, H in metres, n ≈ 0.3 to 0.8
  • Stone column area replacement ratio, triangular grid: a_s = 0.907 (d / s)²
  • Consolidation time scales with (drainage path)²
Common mistake

Removing the surcharge before the measured settlement and pore pressures show the target consolidation.

Solved example

Problem. A 15 t pounder is dropped from 20 m. With n = 0.5, estimate the depth of improvement. Separately, find the area replacement ratio for 0.9 m stone columns at 2.0 m triangular spacing.

  1. D ≈ 0.5 × √(15 × 20) = 0.5 × √300 = 0.5 × 17.32 = 8.7 m.
  2. a_s = 0.907 × (0.9 / 2.0)² = 0.907 × 0.2025 = 0.184.
  3. About 18 percent of the plan area is replaced by stone.
  4. Both values are first estimates; field trials confirm them.

Answer. Depth of improvement about 8.7 m; area replacement ratio about 0.18

Quick quiz

1How do vertical drains speed up consolidation?

They shorten the drainage path, and time grows with its square.

2Which method suits deep loose sand over a large area?

Dynamic compaction or vibro-compaction.

3Which Indian standard gives stone column guidance?

IS 15284 (Part 1).

Code note
  • IS 15284 (Part 1) (India): Design and construction for ground improvement: guidelines, stone columns.
  • EN 1997 (Eurocode 7) (Europe): Geotechnical design.

Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • B. M. Das, Principles of Foundation Engineering, Cengage, latest edition.
  • J. E. Bowles, Foundation Analysis and Design, McGraw Hill, 5th edition.
  • M. J. Tomlinson, J. Woodward, Pile Design and Construction Practice, CRC Press, latest edition.