Well foundations

Intermediate Geotechnical and Foundation Engineering Reviewed 24 Oct 2026 2 min read

A well foundation is a large hollow caisson sunk through river sand and silt to a firm stratum well below the deepest scour. It is the traditional deep foundation for bridges over India's big alluvial rivers, where floods scour the bed many metres deep and loose sand extends far down. Its large size and mass give it high resistance to lateral loads from water current, braking and earthquakes.

A well is built from the bottom up. A steel cutting edge with a sharp lower face is laid at bed level or on an island, a reinforced concrete curb is cast on it, and the steining, the thick wall of the well, is raised in lifts. Soil is dredged from inside, by grab or by divers in difficult conditions, so that the well sinks under its own weight, aided by kentledge when skin friction is high. Once it reaches founding level, a concrete bottom plug is placed, the inside is partly filled with sand, a top plug is cast and a well cap carries the pier.

Diagram: Indiacon original, not to scale.

Sinking must be controlled. Uneven dredging or obstructions make the well tilt or shift from its intended position; tilts and shifts beyond the permissible limits require design rechecks. Sand blows into the well, boulders and buried logs are typical problems.

Design starts with the scour depth, estimated for alluvial beds from the design discharge per metre width and a silt factor using Lacey's relation. Maximum scour around piers is taken as a multiple of the normal scour depth, and the well must reach a grip length below the maximum scour level. Stability against lateral loads is checked by considering soil resistance on the embedded part. In India these rules are given in IRC 78.

Tip

Dredge evenly and record tilt and shift after every lift; early correction is far easier.

Key formulas
  • Lacey normal scour depth: d_sm = 1.34 (D_b² / K_sf)^(1/3) (D_b = discharge per metre width in m³/s/m, K_sf = silt factor)
  • Maximum scour at a pier (IRC practice): 2 d_sm below high flood level
Common mistake

Using the normal scour depth instead of the maximum scour depth to fix the founding level.

Solved example

Problem. A bridge has a design discharge intensity of 10 m³/s per metre width over an alluvial bed with silt factor 1.0. Find the normal scour depth and the maximum scour depth at a pier.

  1. d_sm = 1.34 × (10² / 1.0)^(1/3) = 1.34 × 100^(1/3) = 1.34 × 4.642 = 6.22 m.
  2. Maximum scour depth at a pier = 2 × 6.22 = 12.44 m below high flood level.
  3. The well must be founded below this level by the grip length specified in the code, and checked for stability.

Answer. Normal scour 6.2 m; maximum scour at the pier about 12.4 m below HFL

Quick quiz

1Why are wells used for bridges over alluvial rivers?

They reach below deep scour and resist large lateral loads.

2What is the steining?

The thick wall of the well.

3Name two problems during sinking.

Tilt and shift (also sand blows and obstructions).

Code note
  • IRC:78 (India): Foundations and substructure of road bridges.
  • IS 1904 (India): Design and construction of foundations in soils: general requirements.

Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • B. M. Das, Principles of Foundation Engineering, Cengage, latest edition.
  • J. E. Bowles, Foundation Analysis and Design, McGraw Hill, 5th edition.
  • M. J. Tomlinson, J. Woodward, Pile Design and Construction Practice, CRC Press, latest edition.