1.2 Temporary facilities and access
- Plan the zones for site offices, laboratory, stores, plant, labour camp and work fronts so that they do not conflict with traffic or drainage.
- List the temporary access, barricading and lighting measures needed before work starts beside a public road.
- State the sanitation, drinking-water and first-aid expectations for construction camps, citing MoRTH Section 100.
- Prepare an illustrative site-layout sketch and a simple access-road quantity check for a learning example.
Overview
Temporary facilities are the offices, stores, plant yards, camps, laboratories and access roads that make a site workable. They are not the permanent works, but they strongly affect safety, quality, programme and neighbour relations. A crowded gate, a camp without sanitation, or a haul road that crosses live traffic without control will show up as accidents, delays and rejected work.
Government specifications for road and bridge works in India treat these items as part of the contractor’s general obligations. The MoRTH Specifications for Road and Bridge Works (5th Revision, 2013), Section 100, require suitable accommodation for staff and workmen with adequate sanitary arrangements and first-aid, leave the contractor to arrange land for offices, laboratory, plant and camps, and require construction camps to meet applicable national and state building regulations with proper wastewater handling. Traffic safety during construction, including barricades, signs and lighting, is covered in the same section.
CPWD Specifications 2019 (Vol. 1) add the site-level rule that excavations directed by the Engineer-in-Charge must be securely barricaded and lit, and that existing services must be protected. This lesson uses those official requirements as the teaching frame for laying out a site. It is an educational template, not a site-specific method statement or approval.
Method step by step
- Study the contract drawings, right-of-way, environmental management plan and any land available outside the permanent works. Confirm what the Employer provides and what the contractor must arrange (MoRTH 2013 cl. 108.3).
- Sketch a site layout: gate and security, site office and first-aid, field laboratory, stores (with bunded fuel and bitumen areas), plant (batching, crushing, hot mix as applicable), labour camp, parking, and clear haul routes to each work front.
- Keep camps and plant away from live carriageways and from neighbouring dwellings where noise and dust would be a nuisance (MoRTH 2013 cl. 111.8.4). Separate clean water supplies from wastewater drainage.
- Provide drinking water and sanitary accommodation for employees and workers, and maintain them in a neat condition to meet Central, State and local rules (MoRTH 2013 cl. 111.8.4). Send camp wastewater to soak pits and treat human excreta through septic tanks before discharge, as the same clause requires.
- Build temporary access and haul roads of adequate width and strength for the plant that will use them; keep dust down by watering where needed (MoRTH 2013 cl. 112.5 on temporary travelled ways).
- Where work affects a public highway, submit and agree a traffic management plan before starting. Erect and maintain barricades, signs, markings, flags, lights and flagmen as approved (MoRTH 2013 cl. 112.4). Barricades closing a carriageway are painted with alternate black and white stripes and carry red lanterns or warning lights from sunset to sunrise.
- Barricade and light excavations as required by CPWD 2019 cl. 2.3.1; protect existing services before driving posts or digging (cl. 2.3.2).
- Locate the field laboratory preferably next to the site office (MoRTH 2013 on field laboratories). Stock first-aid equipment at accessible points.
- Record the layout of quarry sites, plant sites, camps and access roads as project records (MoRTH 2013 cl. 121.2). Describe locations of site facilities in the general part of the method statement (cl. 115.2).
- Get the Engineer’s approval to the layout and the traffic arrangements before major plant or camp occupation starts; update the plan when the work front moves.
Where used and limits
- Used on every building, road, bridge, metro and industrial site that needs offices, plant or a workforce camp.
- Compact urban sites may place offices in rented rooms and omit a residential camp; rural highway packages usually need both plant yards and camps.
- Temporary diversions (MoRTH 2013 cl. 112.3) are used when traffic cannot share the working width; part-width working with one-way control is the alternative.
- Limits: a layout that ignores monsoon drainage floods the camp; fuel stored without a bund contaminates soil and water; barricades removed before the hazard is gone put the public at risk.
Equipment (generic)
- Temporary buildings or portable cabins for offices, first-aid and laboratory; lockable stores; bunded tanks for fuel and bitumen.
- Water tanks, pipelines or tankers for drinking and construction water; septic tanks and soak pits for camp wastewater.
- Barricades, reflective signs, drums or cones, warning lights or lanterns, flagmen equipment for traffic control.
- Graders, rollers and tippers to build and maintain haul roads and diversions (named by function only).
- Fire extinguishers, first-aid kits and PPE issue points at offices and work fronts.
Clauses are paraphrased and cited by number only.
- Site layout and locations of batching plant, hot mix plant, crushing plant and related facilities stated in the general method statement and accepted by the Engineer (MoRTH 2013 cl. 115.2).
- Construction camp arrangement checked against noise, wastewater and sanitary rules of MoRTH 2013 cl. 111.8.4 and against applicable national/state building regulations named in that clause.
- Occupational health and safety procedures for quarry, plant, work and camp sites submitted (MoRTH 2013 cl. 111.9).
- Traffic management plan agreed before construction that affects the highway; barricades, signs and lights maintained until the Engineer authorises removal (MoRTH 2013 cl. 112.4–112.5).
- Excavations barricaded and lit as required (CPWD 2019 cl. 2.3.1); services protected (cl. 2.3.2).
- Digital records of camp sites, plant sites and access roads kept and updated (MoRTH 2013 cl. 121.2).
- Field notes and layout drawings signed; changes to the layout re-approved before they are occupied.
- Separate people from plant: marked walkways, speed limits on haul roads, and no living quarters inside the swing radius of cranes or the dust plume of crushers.
- Store fuel and bitumen in bunded areas away from drains and camps; control ignition sources.
- Provide drinking water and toilets from day one; do not wait until the camp is “finished”.
- Keep barricades and lights in place whenever a drop-off, trench or narrowed carriageway remains (MoRTH 2013 cl. 112.4).
- First-aid and emergency contacts posted at the office and at each work front; OHS procedures cover camps as well as work sites (cl. 111.9).
- This lesson is educational. Follow the site-specific method statement, statutory rules and the instructions of a competent supervisor.
- Putting the labour camp uphill of the works so that camp wastewater drains into foundations or a watercourse.
- Opening a gate onto a highway without an agreed traffic management plan, signs and flagmen.
- Removing barricades at night to make plant access easier while the hazard is still there.
- Storing diesel in unbunded drums next to a soak pit or well.
- Crowding the batching plant against the site office so that dust and noise make the laboratory unusable.
- Omitting the camp and plant layout from the method statement, then arguing about space after plant arrives.
Worked examples
Illustrative numbers for learning, not data from a real project. Every value was recomputed before publication.
Problem. A contractor may use a rectangular plot 200 m along a highway and 100 m deep (2.0 ha) for temporary facilities. Reserve a 20 m deep strip along the highway for a gate, parking and a planted dust screen. Place the office and laboratory in a 40 m × 30 m block near the gate, the plant yard in a 80 m × 50 m block at the far corner, and the labour camp in a 60 m × 40 m block on the remaining side, leaving a 6 m haul road loop. Find the area of each zone and the area left as open working space.
- Plot area = 200 × 100 = 20 000 m².
- Highway strip = 200 × 20 = 4 000 m².
- Office + laboratory block = 40 × 30 = 1 200 m².
- Plant yard = 80 × 50 = 4 000 m².
- Labour camp = 60 × 40 = 2 400 m².
- Sum of named zones = 4 000 + 1 200 + 4 000 + 2 400 = 11 600 m².
- Remaining open / haul / buffer ≈ 20 000 − 11 600 = 8 400 m² (about 42 percent). Check that the camp drainage does not flow toward the plant or the highway drain.
Answer. Named zones 11 600 m²; about 8 400 m² left as open working space
Problem. A 180 m length of two-lane highway is closed for a bridge approach. A temporary diversion is built beside it with a 7 m carriageway and 2.5 m earthen shoulders each side (MoRTH 2013 cl. 112.3 dimensions used as teaching values). The diversion length including tapers is 220 m. Find the paved carriageway area and the shoulder area.
- Carriageway area = 7.0 × 220 = 1 540 m².
- Shoulders = 2 × 2.5 × 220 = 1 100 m².
- Total formation width = 7 + 2 × 2.5 = 12 m; formation area = 12 × 220 = 2 640 m² (= 1 540 + 1 100).
- These are plan areas for learning; real quantities also need crossfall, drainage and junction fillets from the approved diversion drawing.
Answer. Carriageway 1 540 m²; shoulders 1 100 m²; formation 2 640 m²
Problem. A camp houses 120 workers. For planning only, assume 70 litres per person per day for drinking, cooking and washing (an illustrative planning figure, not a statutory allotment). Find the daily demand and the volume of a storage tank that holds two days’ supply with 20 percent spare.
- Daily demand = 120 × 70 = 8 400 L/day = 8.4 m³/day.
- Two days’ supply = 16.8 m³.
- With 20 percent spare: 16.8 × 1.20 = 20.16 m³ ≈ 20.2 m³.
- Provide separate drinking water from construction water; keep the septic tank and soak pit downhill of the well or tanker fill point.
Answer. 8.4 m³/day; store about 20.2 m³ for two days with spare
Practice questions
Tap a question to see the answer.
1Why should a labour camp sit away from a crushing plant and a live highway?
To limit noise and dust for workers, and to keep pedestrians and children clear of plant and traffic (MoRTH 2013 cl. 111.8.4).
2Name three items MoRTH 2013 expects around traffic when work occupies a highway.
Barricades, warning signs and lights (also markings, flags and flagmen as in the approved traffic plan) — cl. 112.4.
3A temporary diversion has a 7 m carriageway and 2.5 m shoulders each side. What is the formation width?
7 + 2 × 2.5 = 12 m.
4Where does MoRTH prefer the field laboratory to be located?
Preferably adjacent to the site office of the Engineer / contractor office area.
5What happens to camp wastewater under MoRTH 2013 cl. 111.8.4?
It is discharged into soak pits; human excreta is treated through septic tanks before discharge, conforming to State directives.
6List two CPWD 2019 protections that also apply when temporary access trenches are dug.
Barricade and light the excavation (cl. 2.3.1); protect existing services (cl. 2.3.2).
Sources
Official and authoritative sources, listed in no order of merit. Our explanations, diagrams and examples are original.
- Ministry of Road Transport and Highways (MoRTH), Specifications for Road and Bridge Works, 5th Revision, 2013 (published by the Indian Roads Congress): Section 100 General — scope (accommodation, sanitary arrangements, first-aid); cl. 108.3 land for site offices, laboratory, plant and camps; cl. 111.8.4 Construction Camps; cl. 111.9 Occupational Health and Safety; cl. 112.3–112.5 temporary diversion and traffic safety; cl. 115.2 method-statement site facilities; cl. 121.2 project records of camps and access roads.
- Central Public Works Department (CPWD), Government of India, CPWD Specifications 2019, Vol. 1, Sub-head 2.0 Earth Work: cl. 2.3.1 barricading and lighting; cl. 2.3.2 protection of services. Listed on the CPWD publications page: https://cpwd.gov.in/Documents/cpwd_publication.aspx
- National Building Code of India 2016, Part 7 — Construction Management, Practices and Safety: named only as the national building regulation MoRTH 111.8.4 points to; no NBC clauses are quoted in this lesson because the NBC text was not available on the box for verification this run. NBC 2016 was withdrawn on 30 April 2026 and replaced by SP 7:2026 National Building Construction Standards 2026 (BIS); check the construction-safety part of the new edition.
Disclaimer. This lesson is for educational purposes only. Examples and numbers marked "illustrative" are not for design or construction. Standards are paraphrased and may be revised; refer to the current official edition from BIS, IRC or the relevant authority. Real work requires a qualified, licensed engineer, site-specific design, method statements and safety assessments. Indiacon does not rank codes, companies or countries and gives no investment advice. Follow the contract specification, the site-specific method statement, statutory safety rules and the instructions of a competent supervisor. Codes and specifications are cited by number and clause only; no text or tables are reproduced. See our corrections policy.