1.3 Benchmarks and control points
- Explain the difference between a reference (standard) bench mark, a working or temporary bench mark, a change point and a horizontal control point.
- Establish working bench marks tied to the reference bench mark and close every level circuit on a known RL, as required by CPWD 2019 cl. 2.5.1 and 2.11.6.2 and MoRTH 2013 cl. 109.1.
- Check and distribute a level-loop misclosure and record reduced levels in a level book.
- Plan the number and spacing of working bench marks, centre-line references and baseline pillars for a road or building site.
Overview
Every level and position on a site is only as good as the reference it was measured from. Bench marks carry the vertical datum (reduced levels, RL) and control points carry the horizontal positions (coordinates) used to set out the works. If a bench mark settles, is knocked or was never properly tied in, every footing, drain fall and road gradient set from it will be wrong by the same amount.
Indian government specifications make this the first survey task on a contract. CPWD Specifications 2019 (Vol. 1, Sub-head 2.0 Earth Work) ask for a masonry pillar bench mark visible from most of the area, connected to the standard bench mark approved by the Engineer-in-Charge and maintained during the work; for earthwork measurement they add a baseline of permanent masonry pillars and closed level circuits recorded in level books. The MoRTH Specifications for Road and Bridge Works (5th Revision, 2013), cl. 109, ask road and bridge contractors to establish working bench marks tied to the reference bench mark, at a stated density and at structures, to check them monthly and to safeguard all survey monuments.
This lesson explains the method in that official frame. It is an educational template: the bench mark design, tolerances and survey procedure for a real job come from the contract, the approved survey plan and the Engineer.
Method step by step
- Obtain the reference (standard) bench mark value and the survey file or basic traverse data from the Engineer; MoRTH 2013 cl. 109.1 and 109.7 make this the starting point for road works. Check that the reference marks are in place and undisturbed.
- Choose bench mark locations on firm ground outside the excavation, haul routes and spoil areas, and visible from as much of the site as possible (CPWD 2019 cl. 2.5.1). On linear works, plan working bench marks at the density given in MoRTH 2013 cl. 109.1 (four per km) and at or near every drainage structure, over-bridge and underpass.
- Build each bench mark as a protected masonry or concrete pillar with a clear, durable reference point on top (CPWD shows a standard temporary site bench mark in its Fig. 2.1); paint and number it and fence it if plant works nearby.
- Run a closed level loop from the reference bench mark through all new bench marks and back to the start, or to another known RL (CPWD 2019 cl. 2.11.6.2 (3)). Keep backsight and foresight lengths roughly equal and use stable change points.
- Check the arithmetic (sum of backsights minus sum of foresights equals last RL minus first RL) and compute the misclosure. If it is within the limit set in the contract or survey specification, distribute it; if not, re-level.
- Record the adjusted RLs, a sketch and the description of each bench mark in a numbered level book or bound field notebook (CPWD 2019 cl. 2.11.6.1; MoRTH 2013 cl. 109.6), and get the values approved by the Engineer (MoRTH 2013 cl. 109.1).
- For horizontal control, fix a baseline with permanent pillars at spacing not over 150 m and enter its coordinates in the level book (CPWD 2019 cl. 2.11.6.2 (2)); on roads, reference the centre line at 50 m in plain and rolling terrain, 20 m in hilly terrain and at all curve points (MoRTH 2013 cl. 109.3).
- Take original ground levels on a grid (CPWD 2019 cl. 2.5.2: 5 to 15 m intervals as directed, closer at mounds and pits), plot them with the north line and bench mark positions, and have the plans signed before earthwork starts (cl. 2.5.2, 2.11.6.2 (4)).
- Recheck working bench marks every month and record any approved adjustment (MoRTH 2013 cl. 109.1); recheck at once after any knock, flooding, blasting nearby or visible settlement.
- Never move or remove a reference peg or bench mark without the Engineer’s approval (MoRTH 2013 cl. 109.5); re-establish missing or disturbed traverse points before using them (cl. 109.7).
Where used and limits
- Used on every building, road, bridge, pipeline, canal and metro site before any excavation or setting out.
- Buildings usually need one or two well-protected site bench marks and a baseline; long linear works need a chain of working bench marks and centre-line references along the route.
- Satellite positioning (GNSS) and total stations now carry most horizontal control, but levels for drainage, floors and bearings are still normally checked by spirit or digital levelling from bench marks.
- Limits: a bench mark on fill, near a vibrating plant or in an excavation zone will move; a loop that is not closed hides errors; a value copied without checking the reference may be on a different datum from the drawings.
Equipment (generic)
- Automatic or digital level with a graduated staff; a staff bubble and a change-plate (or stable peg) for change points.
- Total station or GNSS receiver for coordinates of control pillars and traverse points (named by function only).
- Steel tape for short checks and pillar dimensions; marker paint and number plates.
- Masonry, concrete or steel pins set in concrete for bench mark and control pillars; protective fencing where plant works close by.
- Numbered level books or bound field notebooks; site sketches of each mark. Suits when… a level is preferred for precise height differences over short distances; a total station or GNSS suits wider areas and coordinates.
Clauses are paraphrased and cited by number only.
- Working bench marks tied to the reference bench mark, approved by the Engineer, checked monthly, with an up-to-date record shared with the Engineer (MoRTH 2013 cl. 109.1).
- Bench mark pillar built to the approved design and connected with the standard bench mark; profiles and pegs maintained during excavation (CPWD 2019 cl. 2.5.1).
- Every level circuit closed on the starting point or another known RL (CPWD 2019 cl. 2.11.6.2 (3)); arithmetic check done on every page.
- Baseline pillars at not more than 150 m with coordinates entered and maintained till final payment (CPWD 2019 cl. 2.11.6.2 (2)).
- Original ground levels recorded in the level book, signed by both parties and test-checked as specified (CPWD 2019 cl. 2.11.6.2 (1), 2.11.6.3).
- Centre-line references placed at the stated intervals and kept until finished formation level is accepted (MoRTH 2013 cl. 109.3); no reference peg moved without approval (cl. 109.5).
- Field notes kept in bound notebooks open to inspection (MoRTH 2013 cl. 109.6).
- Stand clear of moving plant when levelling on a live site; use a second person as a lookout near haul roads.
- Do not level from the edge of an open excavation; keep staff positions behind barriers and away from unsupported sides.
- On highway sites, work inside the agreed traffic management arrangement, wear high-visibility clothing and never stand in a live lane to read the staff.
- Take care with metal staffs near overhead power lines.
- This lesson is educational and is not a site-specific method statement; follow the approved survey plan, statutory rules and the instructions of a competent supervisor.
- Building the site bench mark on loose fill or inside the future excavation, so it settles or is dug out.
- Running an open (unclosed) level line and trusting the last RL without any check.
- Using a change point that moves (a loose stone or soft ground) between the foresight and the next backsight.
- Distributing a large misclosure instead of re-levelling when it is outside the specified limit.
- Recording levels on loose sheets instead of a numbered level book, so the history of a bench mark is lost.
- Moving a centre-line reference peg for plant access without approval and then setting out from its new position.
Worked examples
Illustrative numbers for learning, not data from a real project. Every value was recomputed before publication.
Problem. A closed loop starts and ends at BM A (RL 100.000 m) through TBM1, TBM2 and a change point CP. Readings (m): S1 BS 1.425 on BM A, FS 1.120 on TBM1; S2 BS 1.640 on TBM1, FS 0.985 on TBM2; S3 BS 1.210 on TBM2, FS 2.170 on CP; S4 BS 0.890 on CP, FS 0.902 on BM A. Loop length 1.2 km. Take an illustrative project limit of 12√K mm (K in km). Find the RLs, the misclosure and the adjusted RLs, distributing equally per set-up.
- S1: rise = 1.425 − 1.120 = 0.305 m; RL TBM1 = 100.305 m.
- S2: rise = 1.640 − 0.985 = 0.655 m; RL TBM2 = 100.960 m.
- S3: fall = 1.210 − 2.170 = −0.960 m; RL CP = 100.000 m.
- S4: fall = 0.890 − 0.902 = −0.012 m; computed RL BM A = 99.988 m.
- Check: ΣBS = 5.165, ΣFS = 5.177, ΣBS − ΣFS = −0.012 m = 99.988 − 100.000. Misclosure e = −12 mm.
- Limit = 12√1.2 = 13.1 mm; |e| = 12 mm ≤ 13.1 mm, accept and adjust.
- Correction +12/4 = +3 mm per set-up, cumulative: TBM1 100.308 m, TBM2 100.966 m, CP 100.009 m, BM A 100.000 m.
Answer. Misclosure −12 mm (within 13.1 mm); adjusted RLs TBM1 100.308 m, TBM2 100.966 m
Problem. A 7.5 km highway section has 6.3 km in plain terrain and 1.2 km in hilly terrain, with 3 culverts, 1 minor bridge and 1 underpass. Using MoRTH 2013 cl. 109.1 (four working bench marks per km plus marks at or near each structure) and cl. 109.3 (centre-line references at 50 m in plain and 20 m in hilly terrain), estimate the number of working bench marks and centre-line reference intervals, before adding curve points.
- Bench marks along the route = 4 × 7.5 = 30.
- At or near structures = 3 + 1 + 1 = 5 (if none coincides with a route mark).
- Working bench marks ≈ 30 + 5 = 35.
- Plain-terrain reference intervals = 6 300 / 50 = 126.
- Hilly-terrain intervals = 1 200 / 20 = 60.
- Total = 186 intervals, so about 187 reference stations along the line, plus every curve point as directed.
Answer. About 35 working bench marks; about 187 centre-line reference stations plus curve points
Problem. A building plot is 60 m × 45 m and its baseline runs 620 m from the site gate along a boundary to the far reference. Using CPWD 2019 cl. 2.11.6.2 (2) (baseline pillars at not more than 150 m) and cl. 2.5.2 (ground levels at 5–15 m intervals), find the minimum number of baseline pillars and the number of grid points at 15 m and at 7.5 m spacing over the plot.
- Intervals ≥ 620 / 150 = 4.13, so 5 intervals; pillars = 5 + 1 = 6 at 124 m spacing.
- Grid at 15 m: (60/15 + 1) × (45/15 + 1) = 5 × 4 = 20 points.
- Grid at 7.5 m: (60/7.5 + 1) × (45/7.5 + 1) = 9 × 7 = 63 points.
- Closer spacing is used where mounds, pits or undulations are found (cl. 2.5.2).
Answer. 6 baseline pillars at 124 m; 20 grid points at 15 m or 63 at 7.5 m
Practice questions
Tap a question to see the answer.
1What is the difference between a reference bench mark and a working bench mark?
The reference bench mark carries the official datum value given in the contract; working bench marks are set on site, tied to it by levelling and approved, and used day to day (MoRTH 2013 cl. 109.1).
2How often should working bench marks on a MoRTH road contract be checked?
Once every month, with any adjustment approved and recorded (cl. 109.1).
3A loop gives ΣBS = 6.240 m and ΣFS = 6.231 m, starting and closing on the same BM. What is the misclosure?
+0.009 m = +9 mm (closing RL is 9 mm high), so a correction of −9 mm is distributed.
4What is the maximum spacing of baseline pillars for earthwork measurement under CPWD 2019?
Not more than 150 m (cl. 2.11.6.2 (2)).
5At what intervals is a road centre line referenced in hilly terrain under MoRTH 2013 cl. 109.3?
Every 20 m, and at all curve points.
6Why must a level circuit be closed?
Closing on the start point or another known RL exposes reading, booking and change-point errors that an open line would hide (CPWD 2019 cl. 2.11.6.2 (3)).
Sources
Official and authoritative sources, listed in no order of merit. Our explanations, diagrams and examples are original.
- Central Public Works Department (CPWD), Government of India, CPWD Specifications 2019, Vol. 1, Sub-head 2.0 Earth Work: Burjis (terminology); cl. 2.5.1 bench mark pillar connected to the standard bench mark (Fig. 2.1 named, not reproduced); cl. 2.5.2 ground levels and signed plans; cl. 2.11.6.1–2.11.6.3 level books, baseline pillars, closed circuits and test checks. Listed on the CPWD publications page: https://cpwd.gov.in/Documents/cpwd_publication.aspx
- Ministry of Road Transport and Highways (MoRTH), Specifications for Road and Bridge Works, 5th Revision, 2013 (published by the Indian Roads Congress), Section 100 General: cl. 109.1 working bench marks; cl. 109.3 centre-line referencing; cl. 109.5 reference pegs; cl. 109.6 survey monuments and field notebooks; cl. 109.7 traverse points and survey file.
Disclaimer. This lesson is for educational purposes only. Examples and numbers marked "illustrative" are not for design or construction. Standards are paraphrased and may be revised; refer to the current official edition from BIS, IRC or the relevant authority. Real work requires a qualified, licensed engineer, site-specific design, method statements and safety assessments. Indiacon does not rank codes, companies or countries and gives no investment advice. Follow the contract specification, the site-specific method statement, statutory safety rules and the instructions of a competent supervisor. Codes and specifications are cited by number and clause only; no text or tables are reproduced. See our corrections policy.