1.1 Site clearance, benchmarks and setting out of a building
- Describe the order of work from site clearance to a set-out building ready for excavation.
- Establish a site benchmark, take ground levels and transfer a reduced level to a profile peg.
- Set out a rectangular building by the centre-line method and prove it square with a diagonal check.
- List the QA/QC checks and safe site practices that apply before any trench is dug.
Overview
Every structure starts as lines on a drawing. Setting out is the work that puts those lines on the ground in the right place, at the right level and square to each other. Errors made at this stage are copied into every footing, column and wall that follows, so the few hours spent on careful setting out are some of the most valuable on a project.
Before setting out, the area is cleared so that pegs, profiles and later the excavation sit on firm, clean ground. A permanent site benchmark is then fixed and tied to an approved reference benchmark, so that every level on the job refers to one known value. Only then are the centre lines, corners and trench edges marked.
Government specifications in India describe these steps in plain terms. The CPWD Specifications 2019 (Vol. 1, sub-head 2.0 Earth Work) cover site clearance, protection of services and adjoining work, a masonry benchmark pillar and profiles before earthwork starts. The MoRTH Specifications for Road and Bridge Works (5th Revision, 2013) cover setting out of road works through working benchmarks, centre-line referencing and bound field notes. This lesson follows the same logic for a small building.
Method step by step
- Study the drawings: the site plan with grid or coordinates, the foundation plan with centre lines and the levels (plinth, formation, finished floor). Confirm the reference benchmark and its value with the engineer.
- Clear the area of shrubs, small trees, grass and rubbish, and remove roots to the depth the specification requires (CPWD 2019 cl. 2.4.1 sets the depth relative to ground, formation and subgrade levels; larger trees are cut only with written permission, cl. 2.4.2).
- Locate and protect existing services and adjoining structures before any digging (CPWD 2019 cl. 2.3.2); barricade and sign excavation zones, with lighting at night (cl. 2.3.1).
- Build the site benchmark pillar where it can be seen from most of the site and connect it to the approved standard benchmark by a closed levelling run (CPWD 2019 cl. 2.5.1).
- Take ground levels on a grid, typically at 5 to 15 m spacing on uniform ground and closer where the ground is uneven, record them in the field book and plot them; the level plan is signed before earthwork starts (CPWD 2019 cl. 2.5.2).
- Mark a baseline (usually the front centre line, or a grid line from the site plan) with two well-founded pegs. From it, set out the other centre lines at right angles using a total station, a theodolite or, for small work, the 3-4-5 triangle with a steel tape.
- Fix pegs at the corners. Check the building is square by measuring both diagonals: for a rectangle they must be equal, and both must agree with the value from the drawing.
- Erect profiles (boards on posts, or masonry Burjis) outside the trench line at each corner and at cross walls, with nails or saw cuts marking the centre line, trench width and wall width. Stretch strings between profiles to re-create the lines at any time.
- Transfer the level: mark the top of each profile or a reference peg at a known reduced level from the benchmark, so the excavation depth can be checked with a staff or a boning rod.
- Mark the trench edges on the ground with lime or chalk from the strings, get the layout checked independently and approved, then hand over for excavation.
Where used and limits
- Used on every building, plant, pavement and bridge site; for linear works (roads, pipelines) the same ideas are applied to a centre line with chainage, which a later lesson covers.
- The centre-line method suits load-bearing walls and strip footings; for framed buildings the column grid is set out instead, and each footing is set out from grid lines.
- Tape-and-triangle methods are adequate for small, flat sites with short distances. For large or sloping sites, many grid lines, curved geometry or tall structures, instrument methods (total station, GNSS for control) are needed.
- Limits: profiles disturbed by plant or traffic give wrong lines; long tape measurements on slopes need slope correction and proper tension; a single benchmark without a check run can carry an error into every level.
Equipment (generic)
- Hand tools and light plant for clearance; a crawler or wheeled dozer with a ripper where vegetation and stumps are heavy (MoRTH 2013 cl. 201.3 describes this use).
- Levelling instrument (automatic or digital level) with a graduated staff, for the benchmark run, ground levels and level transfer.
- Total station or theodolite with a steel tape for angles and distances; GNSS receivers for site control on large sites.
- Steel tapes (not cloth tapes), pegs, nails, profile boards on posts or masonry pillars (Burjis), string line, plumb bob, spirit level, lime or chalk for marking.
- Boning rods (travellers) for checking excavation depth between profiles.
Clauses are paraphrased and cited by number only.
- Benchmark: closed levelling run from the approved reference benchmark and back, with the closing difference within the tolerance in the contract; the benchmark is protected and maintained (CPWD 2019 cl. 2.5.1).
- Ground levels taken and plotted before earthwork and the level plan signed by both parties (CPWD 2019 cl. 2.5.2).
- For road and bridge works, working benchmarks are fixed at intervals along the length and near structures and re-checked periodically; the centre line is referenced at regular intervals before earthwork starts (MoRTH 2013 cl. 109.1, 109.3, 109.5).
- Every dimension and level on the drawings is checked on site and any discrepancy reported to the engineer before work proceeds (MoRTH 2013 cl. 109.6).
- Diagonals equal within the tolerance stated in the contract; corner angles confirmed by instrument where the size of the building needs it.
- For piled foundations, the design drawings must give the information needed to set out the piles (IS 2911 (Part 1/Sec 2):2010 cl. 4.2), and pile positions are controlled against the deviation limits of cl. 8.1.2.
- Field notes kept in bound books and signed; layout checked by a second person before excavation (MoRTH 2013 cl. 109.6 on field notes).
- Find and mark buried services (water, sewer, power, telecom) before driving pegs or digging; protect what is found (CPWD 2019 cl. 2.3.2).
- Barricade excavations and mark them with signs by day and lights or reflective paint by night (CPWD 2019 cl. 2.3.1).
- Do not dig below the foundation level of an adjoining building until the underpinning or shoring designed for it is in place (CPWD 2019 cl. 2.3.3).
- Keep survey staff out of the working radius of dozers and excavators; agree a signal person and a safe zone before plant moves.
- Wear the site PPE required by the site rules (helmet, high-visibility vest, safety footwear, gloves when handling pegs and boards).
- This lesson is educational. Follow the site method statement, statutory rules and the instructions of a competent supervisor.
- Setting out from a boundary wall or road edge instead of the approved grid or reference points.
- Checking only the sides of a rectangle and not the diagonals, so an out-of-square building goes unnoticed.
- Fixing profiles too close to the trench, where excavation or plant disturbs them.
- Carrying levels from a single unchecked benchmark, or not closing the level run back on the benchmark.
- Mixing up wall-face lines and centre lines on the profile boards; label every nail or mark.
- Measuring with a sagging or slack tape on sloping ground and not correcting for slope.
- Starting excavation before the layout is independently checked and approved.
Worked examples
Illustrative numbers for learning, not data from a real project. Every value was recomputed before publication.
Problem. A building is set out by centre lines as a 15.000 m × 9.000 m rectangle ABCD. Find the design diagonal. On site the diagonals measure 17.513 m (AC) and 17.493 m (BD). Estimate the angular error at the corner and the offset it causes at the far end of the 9 m side.
- Design diagonal d = √(15.000² + 9.000²) = √306.000 = 17.493 m.
- For a parallelogram with sides a and b and corner angle 90° + δ, d₁² − d₂² = 4ab sin δ.
- sin δ = (17.513² − 17.493²)/(4 × 15 × 9) = 0.70012/540 = 0.001297.
- δ = 0.0743° ≈ 4.5 minutes of arc.
- Offset at the end of the 9 m side = 9 000 × 0.001297 ≈ 11.7 mm. The building is not square; reset corners until both diagonals read 17.493 m within the contract tolerance.
Answer. d = 17.493 m; δ ≈ 0.074° (4.5′); about 12 mm out at 9 m
Problem. The site benchmark has RL 100.000 m. A level reads 1.235 m on the benchmark (back sight) and 0.875 m on a profile peg (fore sight). The bottom of the footing levelling course is at RL 98.600 m and the plinth top at RL 100.450 m. Find the RL of the peg, the depth to dig below the peg and the plinth height above it.
- Height of instrument HI = 100.000 + 1.235 = 101.235 m.
- RL of peg = 101.235 − 0.875 = 100.360 m.
- Depth to formation below peg top = 100.360 − 98.600 = 1.760 m.
- Plinth top above peg top = 100.450 − 100.360 = 0.090 m.
- Close the run: read the benchmark again from a second set-up and confirm it returns RL 100.000 m within tolerance.
Answer. Peg RL 100.360 m; dig 1.760 m below it; plinth 0.090 m above it
Problem. The 15 m × 9 m building has outer wall trenches 1.2 m wide and 1.5 m deep on level ground, and one 9 m cross wall (centre line) with the same trench, meeting the long walls at two T-junctions. Find the trench volume by the centre-line method and the machine time for an assumed effective output of 40 m³/h (an illustrative planning figure, not a machine rating).
- Outer centre-line length = 2 × (15 + 9) = 48.0 m. For a closed rectangle the corners need no correction: plan area = 48.0 × 1.2.
- Outer trench volume = 48.0 × 1.2 × 1.5 = 86.40 m³.
- Cross-wall trench length = 9.0 − 2 × (1.2/2) = 7.8 m (half the trench width deducted at each T-junction).
- Cross-wall volume = 7.8 × 1.2 × 1.5 = 14.04 m³; total = 86.40 + 14.04 = 100.44 m³.
- Machine time ≈ 100.44/40 = 2.5 h, plus time for trimming the trench bottom by hand and for checks.
Answer. ≈ 100.4 m³; about 2.5 h of excavator time at the assumed 40 m³/h
Practice questions
Tap a question to see the answer.
1A rectangle is set out 12.000 m × 5.000 m. What should each diagonal measure?
√(144 + 25) = 13.000 m.
2Using the 3-4-5 rule with a 20 m tape, give a convenient set of lengths for a right angle.
Multiply by 3: 9 m, 12 m and 15 m.
3BM RL 50.000 m, back sight 1.420 m, fore sight on a peg 2.065 m. Find the peg RL.
HI = 51.420 m; peg RL = 51.420 − 2.065 = 49.355 m.
4A road 3.6 km long in plain terrain: if the centre line is referenced every 50 m, how many reference points are needed on the straight (both ends included)?
3 600/50 = 72 intervals, so 73 points, plus all curve points.
5Why are profiles set back outside the trench instead of at the corner pegs?
Corner pegs are lost when the trench is dug; set-back profiles survive and let the lines be re-strung at any time.
6Two diagonals of a set-out rectangle differ by 25 mm. Is the building square? What do you do?
No. Re-check the baseline, reset the corner pegs until both diagonals equal the design value within the contract tolerance, then re-check independently.
Sources
Official and authoritative sources, listed in no order of merit. Our explanations, diagrams and examples are original.
- Central Public Works Department (CPWD), Government of India, CPWD Specifications 2019, Vol. 1, Sub-head 2.0 Earth Work: cl. 2.3 Protections, cl. 2.4 Site clearance, cl. 2.5 Setting out and making profiles. Listed on the CPWD publications page: https://cpwd.gov.in/Documents/cpwd_publication.aspx
- Ministry of Road Transport and Highways (MoRTH), Specifications for Road and Bridge Works, 5th Revision, 2013 (published by the Indian Roads Congress): cl. 109 Setting out; cl. 201 Clearing and grubbing.
- IS 2911 (Part 1/Sec 2):2010 Design and construction of pile foundations: bored cast in-situ concrete piles, cl. 4.2 and cl. 8.1.2 (cited by number only).
Disclaimer. This lesson is for educational purposes only. Examples and numbers marked "illustrative" are not for design or construction. Standards are paraphrased and may be revised; refer to the current official edition from BIS, IRC or the relevant authority. Real work requires a qualified, licensed engineer, site-specific design, method statements and safety assessments. Indiacon does not rank codes, companies or countries and gives no investment advice. Follow the contract specification, the site-specific method statement, statutory safety rules and the instructions of a competent supervisor. Codes and specifications are cited by number and clause only; no text or tables are reproduced. See our corrections policy.